Rohini Engineering & Builders · Ward 14 · Client rates
Amrit Rawat
Cost Planning / Rate Assumptions
Client-specific built-up/plinth pricing, actual trade measurement and wages in a read-only planning register. Edited values originate from the project's single native Google Sheet; publication uses a checked, versioned snapshot.
USER-SUPPLIED INDICATIVE · NOT ENGINEER APPROVEDPlinth-area rates—
On-site trade rates—
Daily wage rates—
Published version—
Explore rate ranges
NPR amounts. Choose a measurement family or search by work, basis, unit or rate ID. No inclusive package is added to its component trade prices.
| Rate ID | Work / Trade | Basis | Low NPR | High NPR | Actual Unit | Scope / notes |
|---|
Loading governed public snapshot…
Measurement and contract boundaries
- Plinth-area rates use built-up square feet, not wall/tile measured area.
- Trade rates use actual site measurements such as points, installed floor/wall area, running feet and bathrooms.
- Daily wages are per worker-day, not subcontractor lump sums.
- Labour only and material + labour are alternative pricing arrangements.
- Turnkey and grey-civil scopes may overlap with finish/MEP trades; never total them together without a contract scope reconciliation.
- Painting wall area ≈ 3.5 × plinth is only a rough assumption; use measured actual area for a quotation.
- Taxes, transport, contractor margin, site conditions, project quantities and material grades require separate verification.
Source governance: A9 Rohini Project / Ward 14 holds the editable Google Sheet. This website contains only approved-to-present indicative rate data, not the private Sheet ID, client finance or document permissions.